Quick answer

FAIRWAYS builds G+4 residential, commercial and mixed-use buildings in the UAE as a turnkey contract covering foundations, frame, floor-by-floor MEP, façade, fit-out and Civil Defence completion. A typical G+4 takes 14–22 months.

A G+4 building is ground plus four upper floors: typically retail or parking at ground, apartments or offices above. It is the largest building that most private developers in the Northern Emirates build, and the one where sequencing across trades decides the finish date.

The 3D model above shows how we plan it: frame first, then MEP floor by floor, façade closing behind it, finishes following the façade.

G+4 scope

  • Piling or raft foundations, basement if required
  • RC frame at 2–3 weeks per floor
  • Lift, stair and service cores
  • Floor-by-floor MEP, risers and plant
  • Curtain wall, windows and ACP façade
  • Apartment and office fit-out
  • Civil Defence, utility and completion certificates
Drone

From the entrance to the whole plot

A visualisation of a completed mixed-use G+4: retail frontage, four residential floors and parking.

MEP close-up

One floor,
every service

In the model, the camera moves into Level 2 while the services go in: chilled-water and drainage risers, ductwork, cable trays, sprinklers and lighting. We set out every floor this way before the ceiling closes.

MEP.1

HVAC

Ducted split or chilled-water fan coils, fresh-air and kitchen and toilet extract.

MEP.2

Plumbing & drainage

Water supply, hot water, soil and waste stacks, roof drainage.

MEP.3

Electrical & ELV

Distribution, lighting, small power, data, CCTV, intercom and access.

MEP.4

Fire

Sprinklers, hose reels, fire alarm and emergency lighting to Civil Defence code.

Programme

14 to 22 months

Indicative for a G+4 of 3,000–6,000 m² built-up area.

StageDurationKey milestone
Design, permits, NOCs3–4 monthsBuilding permit issued
Foundations1.5–2 monthsPlinth beam complete
Frame, G to roof4–6 monthsRoof slab cast
MEP and blockwork4–6 months, overlappingFirst-fix inspections
Façade and finishes4–6 months, overlappingBuilding watertight
Testing, Civil Defence, completion1–2 monthsCompletion certificate
Programme

Fourteen to
twenty-two months

The frame sets the pace: roughly two to three weeks per floor. MEP, blockwork and façade follow floor by floor behind it, so several trades work at once on different levels.

Civil Defence and utility approvals run in parallel from the start, because they decide the completion date.

Indicative G+4 programme
Approvals

Every certificate
on the path

A G+4 passes through more authorities than any other building we deliver. We prepare the submissions, attend inspections and close comments, so approvals never sit on the critical path unnoticed.

Design & compliance →

From design approval to completion certificate
Build style

How it looks
when we finish

The standard we build to, inside and out, from structure to the last finish.

Completed mixed-use G+4 from the air
ExteriorCompleted mixed-use G+4 from the air
Apartment living room with balcony
Interior · ApartmentApartment living room with balcony
Ground-floor shops at dusk
Retail · FrontageGround-floor shops at dusk
Glazing installed floor by floor
Façade · GlazingGlazing installed floor by floor
MEP first fix in the ceiling void
Services · First fixMEP first fix in the ceiling void
FAQ Questions owners ask

Straight answers

What does G+4 mean?

G+4 means a ground floor plus four upper floors, five storeys in total. It is a common height limit for residential and mixed-use plots in many UAE districts.

How long does it take to build a G+4 building in the UAE?

Typically 14–22 months from permit to completion certificate, depending on size, foundations, façade and approvals.

Can a G+4 be built in steel instead of concrete?

Yes, for offices and some commercial uses. Residential G+4 buildings are usually concrete for fire rating and acoustic performance. We advise on the option that fits.

Do you handle Civil Defence approval for G+4 buildings?

Yes. Fire design, inspections and the Civil Defence completion certificate are part of our turnkey scope.

Last updated ·

Have a plot, drawings or just an idea?

Send it. We come back with scope, programme and a priced proposal.

Request a quote →