Warehouses
& PEB steel
Clear-span steel for logistics, industry and cold storage, from foundations to dock doors.
- Largest
- 35,000 m² (2025)
- Structure
- PEB portal frame
- Programme
- 5–9 months
- Includes
- Docks · office · fire
FAIRWAYS builds pre-engineered steel (PEB) warehouses, factories and cold stores across the UAE on a turnkey basis. Our largest single delivery was a 35,000 m² facility in 2025, and a typical 5,000–10,000 m² warehouse takes 5–9 months.
Warehouses earn money from the day they open, so programme matters more than anything. Steel is fabricated while foundations are poured; cladding, MEP and the office block run in parallel.
Warehouse scope
- Portal-frame PEB steel, 30–60 m clear spans
- Insulated roof and wall sandwich panel
- Industrial floor slabs rated for racking
- Dock levellers, shutters, canopies
- Mezzanine and G+1 office block
- Sprinklers, fire alarm, Civil Defence approval
- Yard paving, drainage, boundary wall
Chilled and frozen, built to hold temperature
Insulated panel rooms, rapid-roll doors, anti-condensation floors and refrigeration commissioned before handover.
What we put
under steel
Logistics warehouses
High-bay storage, racking-rated slabs, multiple dock doors and truck yards.
Cold storage
Chiller and freezer rooms from +4 °C to −25 °C in insulated panel.
Factories & workshops
Crane beams, process drainage, three-phase power and ventilation.
Supermarkets
Steel shed with a concrete office block. Leptis Supermarket is underway now.
Showrooms
Glazed fronts with ACP fascias on a steel frame.
Extensions
New steel bays added to live facilities without stopping operations.
Weeks, not years
Indicative for a 5,000–10,000 m² PEB warehouse.
| Stage | Duration | Runs in parallel with | Notes |
|---|---|---|---|
| Design & approvals | 6–10 weeks | — | Steel design by PEB manufacturer |
| Foundations & slab | 6–8 weeks | Steel fabrication | Slab poured after frame |
| Steel erection | 3–6 weeks | Office block structure | Cranes and boom lifts |
| Cladding & roof | 4–6 weeks | MEP first fix | Insulated panel |
| MEP, fire & docks | 6–8 weeks | Floor slab, yard | Civil Defence inspection |
| Handover | 2 weeks | — | Testing and as-builts |
Why steel
is faster
In a PEB building the steel is fabricated in a factory while the foundations are poured on site. Erection then takes weeks, and cladding, services and the office block overlap.
The same warehouse in concrete has to wait for each stage to finish before the next can start.
How it looks
when we finish
The standard we build to, inside and out, from structure to the last finish.




Straight answers
What is a PEB warehouse?
A pre-engineered building (PEB) is a steel structure designed and fabricated in a factory, then bolted together on site. It allows wide column-free spans, fast erection and lower cost per square metre than concrete for large sheds.
How long does it take to build a warehouse in the UAE?
A 5,000–10,000 m² PEB warehouse typically takes 5–9 months from approval to handover. Cold stores add about 4–6 weeks for refrigeration commissioning.
Do you build cold storage facilities?
Yes. We build chilled and frozen rooms in insulated panel from +4 °C to −25 °C, including floors, doors, refrigeration and controls.
What is the largest warehouse you have delivered?
Our largest single turnkey delivery was 35,000 m², completed in 2025. Around 25,000 m² more is under construction in 2026.
Can you extend an existing warehouse while it operates?
Yes. We phase extension works around live operations and separate the work zone for safety.
Last updated ·
Have a plot, drawings or just an idea?
Send it. We come back with scope, programme and a priced proposal.