Quick answer

FAIRWAYS builds pre-engineered steel (PEB) warehouses, factories and cold stores across the UAE on a turnkey basis. Our largest single delivery was a 35,000 m² facility in 2025, and a typical 5,000–10,000 m² warehouse takes 5–9 months.

Warehouses earn money from the day they open, so programme matters more than anything. Steel is fabricated while foundations are poured; cladding, MEP and the office block run in parallel.

Warehouse scope

  • Portal-frame PEB steel, 30–60 m clear spans
  • Insulated roof and wall sandwich panel
  • Industrial floor slabs rated for racking
  • Dock levellers, shutters, canopies
  • Mezzanine and G+1 office block
  • Sprinklers, fire alarm, Civil Defence approval
  • Yard paving, drainage, boundary wall
Cold storage

Chilled and frozen, built to hold temperature

Insulated panel rooms, rapid-roll doors, anti-condensation floors and refrigeration commissioned before handover.

Building types

What we put
under steel

03.1

Logistics warehouses

High-bay storage, racking-rated slabs, multiple dock doors and truck yards.

03.2

Cold storage

Chiller and freezer rooms from +4 °C to −25 °C in insulated panel.

03.3

Factories & workshops

Crane beams, process drainage, three-phase power and ventilation.

03.4

Supermarkets

Steel shed with a concrete office block. Leptis Supermarket is underway now.

03.5

Showrooms

Glazed fronts with ACP fascias on a steel frame.

03.6

Extensions

New steel bays added to live facilities without stopping operations.

Programme

Weeks, not years

Indicative for a 5,000–10,000 m² PEB warehouse.

StageDurationRuns in parallel withNotes
Design & approvals6–10 weeks—Steel design by PEB manufacturer
Foundations & slab6–8 weeksSteel fabricationSlab poured after frame
Steel erection3–6 weeksOffice block structureCranes and boom lifts
Cladding & roof4–6 weeksMEP first fixInsulated panel
MEP, fire & docks6–8 weeksFloor slab, yardCivil Defence inspection
Handover2 weeks—Testing and as-builts
Concrete vs steel

Why steel
is faster

In a PEB building the steel is fabricated in a factory while the foundations are poured on site. Erection then takes weeks, and cladding, services and the office block overlap.

The same warehouse in concrete has to wait for each stage to finish before the next can start.

Same 8,000 m² warehouse · concrete vs PEB
Build style

How it looks
when we finish

The standard we build to, inside and out, from structure to the last finish.

Finished logistics warehouse with docks and truck court
ExteriorFinished logistics warehouse with docks and truck court
High-bay racking on a racking-rated slab
Interior · RackingHigh-bay racking on a racking-rated slab
Cold store at −25 °C with insulated panel and rapid-roll doors
Interior · Cold storageCold store at −25 °C with insulated panel and rapid-roll doors
Sprinklers, cable tray and lighting coordinated overhead
Services · First fixSprinklers, cable tray and lighting coordinated overhead
FAQ Questions owners ask

Straight answers

What is a PEB warehouse?

A pre-engineered building (PEB) is a steel structure designed and fabricated in a factory, then bolted together on site. It allows wide column-free spans, fast erection and lower cost per square metre than concrete for large sheds.

How long does it take to build a warehouse in the UAE?

A 5,000–10,000 m² PEB warehouse typically takes 5–9 months from approval to handover. Cold stores add about 4–6 weeks for refrigeration commissioning.

Do you build cold storage facilities?

Yes. We build chilled and frozen rooms in insulated panel from +4 °C to −25 °C, including floors, doors, refrigeration and controls.

What is the largest warehouse you have delivered?

Our largest single turnkey delivery was 35,000 m², completed in 2025. Around 25,000 m² more is under construction in 2026.

Can you extend an existing warehouse while it operates?

Yes. We phase extension works around live operations and separate the work zone for safety.